§ 28-194. Restoration of pavement.
Unless otherwise specified in the permit, restoration of the asphalt pavement of any street, alley right-of-way or other public place shall be performed by the permittee or by the city, upon request by the permittee. Nothing in this section shall relieve the ROW user from the responsibility to maintain the excavation or installation in a safe condition until it is repaved by city or otherwise restored. in addition to all other applicable fees or charges, if the city performs the repaving of the ROW user shall pay for the repaving based on type of construction repair as per section 28-239.
(1)
No trench shall be opened in any street for the purpose of laying pipes, conduits or ducts more than three hundred (300) feet in advance of the pipe, conduit or ducts being placed in the trench, other than with the prior written consent of the director.
(2)
All excavations shall comply with the city standard technical specification manual.
(3)
Any excavated pavement, debris and other rubble shall be removed, together with any surplus material, within one (1) working day from the time such material is placed upon the street. After backfilling is completed, and prior to repaving the cut, the ROW user shall remove all loose paving material and trim the edges of the excavation at the street surface to the satisfaction of the director.
(4)
Whenever any caving occurs in the sidewalks of any excavation, the pavements above such caving shall be cut away, trench backfilled and pavement restored in accordance with the city standard technical specification manual. In no case shall any side or lateral tamping fill any void under a pavement.
(Ord. No. 2009-O-045, 4-6-09)